September 2025

Quailes Residence

9|8|25 – Welcome Home to the Quailes!!!! It is so nice to work with the many fine homeowner’s we encounter…this family is so grateful. We know you will make so many memories.

8|26|25 – Custom porch railings installed yesterday, final inspections to follow:):).

8|22|25 – The Quails’ Residence is really coming together….final touches and cleaning in the next two weeks….

6|8|25 – Quailes Residence electrical, mechanical & plumbing roughins all complete, insulation complete and plastering to start this coming week. Trim work, interior doors and painting to follow soon !!

3|31|25 – Framing and roofing all finished up at the Quailes Residence!! Water well being installed this week and rough-ins to start soon.

3|20|25 – Update on the framing at the Quailes Residence!

3|13|25 – The extreme cold held up the block mason for a few weeks, but finally finished! Garage slab was poured, and framing has started at the Quailes residence. Hoping for some decent weather !!

2|4|25 – Quailes residence moving along. The recent cold weather delayed the masonry work about 2 weeks, but great progress has been made this week! Sand prep work is starting tomorrow an hope to start framing sometime next week !!

Be sure to follow us on Facebook!

Quailes Residence Read More »